They weren’t lying.

??????????????

It’s not like you can jump into your car and get away from it if you live on Cape Cod. If an accident happens at the Pilgrim nuclear power plant, you have to drive into the danger zone to get away from the Cape, and the Atlantic Ocean pretty much keeps you from driving in the opposite direction.

The chances something could go wrong is increased by the plant having passed it expiration date a number of year ago so it is operating on borrowed time, and it’s being plagued by one problem after another.

In spite of its many problems, the plant is being allowed to stay in operation until 2019.

That gives it a two year window to have an accident. And it only takes one accident to do great damage.

I have driven my car on some very long trips. I used it constantly when I lived on Cape Cod, and any drive to get to anything was a long one. Eventually in spite of the youth of my car and the good mechanical condition of all other parts, the brakes began to give out.

The longer I drove the car the better the chance that at some time when I really did not want them to, the brakes would fail. They never might have, even between when I realized they could, and some future chosen date to have them fixed, I thought I would avoid the possible accident, and get them taken care of.

If my car was an old one, the whole thing could have fallen apart and become useless before the brakes gave completely, but even then, the possibility of a brake failure before I decided to just get rid of the car was there.

And one brake failure could be very harmful not only to me, but whomever or whatever I might have rammed into.

I had attended many meetings at which the problems of the power plant were presented as proof it should be closed down now, but, people could have always dismissed that as alarmist, and the information second hand or exaggerated for self-serving purposes.

But that dismissal loses out when the dangers are presented by those whose opinion cannot be so easily dismissed.

An in-house email was sent recently to Nuclear Regulatory Commission officials in which the leader of a federal inspection team said inspectors are having a hard time interpreting just what they are seeing at the troubled plant.

Donald Jackson, chief of operations at the NRC’s Northeast region and team leader, wrote that while employees might be showing  positive energy,

“it appears many staff across the site may not have the standards to know what ‘good’ actually is. The plant seems overwhelmed just trying to run the station.”

Let me point out that the exposure of the email did not come about from a leak by a disgruntled employee with questionable credentials, but it had been mistakenly sent in an email blast with one of the recipients being the co-founder of the activist group Cape Downwinders, a group that has been active in exposing the problems with the plant and demanding its immediate shut down.

Problems listed in the email are the failure of plant workers to follow established industry procedures, a lack of required expertise among plant experts, broken equipment that never gets properly fixed, the failure of some staff to understand their roles and responsibilities, and a team of employees who appear to be struggling with keeping the nuclear plant running, all things spoken about by those who have been monitoring the plant, including a state senator.

What could have been dismissed as selective and exaggerated criticism has now become an official assessment.

The email includes that:

Plant operators are “very disjointed in their ability to populate meetings and answer questions. Staffing problems seem to impact how fast the licensee can respond.”

“The engineering group appears unprepared to answer all of the questions being posed by the [inspection] team.”

“The corrective actions in the recovery plan seem to have been hastily developed and implemented, and some have been circumvented as they were deemed too hard to complete. We are observing current indications of a safety culture problem that a bunch of talking probably won’t fix.”

Recurring problems with the emergency diesel generators at the plant highlight “poor engineering expertise, no communication with the shift manager and poor corrective action.”

According to Diane Turco of the Cape Downwinders,

“The email preliminary report proves the NRC goal to ‘arrest declining performance’ is not happening at all. Mr. Jackson deserves credit for his candor on the documented dangers the continued operation of Pilgrim presents. Now he needs to lead the way to revoke the operating license.”

Patrick O’Brien, spokesman for Entergy Corp., Pilgrim’s owner-operator, wrote

“We have worked hard to address the issues that led to station performance decline and look forward to demonstrating to the NRC that we have made significant progress in these areas through the inspection process. Until the results of the 95003 Phase “C” inspection and the confirmatory action letter are released, we will not comment on the inspection.”

Translation: Crap. We got caught.

They lost their cover.

The inspection that resulted in the mail was done because of Pilgrim’s standing as one of the worst performing plants in the nation, and the problems it has faced over the years have been dealt with by using band-aid and duct-tape.

For those who want the primary source, here is the email.

Folks,

The following is a brief (or maybe not so brief) update of inspection activities associated with the ongoing Pilgrim 95003 Phase C

 Activities:

The Safety Culture Group conducted additional focus groups today, bringing the total number of people interviewed so far to over 130. This group plans to conduct 1 on 1 chance interviews in plant next week to validate observations from the group discussions 

The Operations NRC inspector observed pre-job briefings and maintenance and operations evolutions in plant 

We can’t female levitra bought here help but think, Our Lady had a direct hand in raising John. Apart from questions about its effectiveness, one of the most common questions would be – cialis discount pharmacy? To be straight, there is no generic name for this is Propecia, and is most commonly used by individuals all all over the globe is Kenpo Martial artistry training. Condenser and Evaporator Malfunction Your HVAC system just female viagra uk couldn’t go without the condenser and evaporator motors. It contains high concentrations of vitamin A and tetracycline, these pills can interrelate with corticosteroids and anti-seizure pills. downtownsault.org cialis prescription Many Engineering discussions over the status of the EDGs 

Many team field activity observations 

Issues/PDs:

(Update) The station performed an apparent cause evaluation for an ‘A’ EDG issue that occurred in September of this year, which involved oil leakage from the ‘A’ EDG blower gear box relief valve fitting. We are still inspecting this issue, but items that we are currently following include: 

Pilgrim only performed a visual inspection of the gear box following the event, even though there are indications that the gear box was potentially run with little or no oil. There are two bearings and a pump in this gear box. We provided this issue as an operability concern to the control room this afternoon. The initial operability determination was “operable” based on the fact that they ran the ’A’ EDG successfully this morning. The NRC Engineering, Maintenance, and Programs group lead does not now have an immediate operability concern, but numerous questions are still being addressed by Pilgrim 

The 50.59 that was performed to install this type of gear box appears to be inadequate, in that it did not account for a new failure mode (i.e., introduction of a relief valve to the gear box) 

Inadequate causal evaluation of the issue (Pilgrim classified the cause as “indeterminate” and missed similar operating experience from North Anna)

Questions on the pre-startup checks for the EDG were resolved by Carey and Erin, as they walked down pre-start up checks with Non Licensed Operators 

Missed reportability call is likely 

The team further questioned the extent of condition of this issue related to the same gear box on the ‘B’ EDG. We believe that there is a current operability question on the ‘B’ EDG related to the same relief valve failure mechanism and leakage. The Pilgrim Systems Engineering Manager stated to the team that the site did not want to remove the EDG from service to investigate this concern as it would result in unavailability time that could place the EDG in Maintenance Rule A.1. Later in the day the Engineering Director and Site VP tried to backtrack on this statement, but the team believes that it was a genuine thought by this senior station manager and is an insight on Safety Culture. Pilgrim is conducting an inspection of this ‘B’ EDG Gear Box this evening. 

The licensee analyzed oil from both the ‘A’ and ‘B’ EDG Blower gear boxes and determined that no component degradation occurred. 

The licensee removed the ‘B’ EDG Gear Box RV, and determined that adequate thread engagement existed, and a common mode failure was unlikely. The reset and reinstalled the RV 

The licensee also ‘staked’ the threads on the ‘B’ EDG Gear Box RV to prevent recurrence of the failure…..However, it appears that the licensee did not perform a 50.59 screening for this modification to SR equipment which is an additional example of 50.59 process performance deficiencies. 

(Update) We are observing evidence of some weaknesses in the use of Subject Matter Experts (SMEs) as a CAPR in the corrective action program area. Specifically, the roles and responsibilities of the SMEs do not appear to be clearly defined (i.e., we are hearing different things from station personnel, the lead CAP SME, and the support CAP SMEs about what their role is). At this point, we do not know if this extends to the other areas or not. The PIR Group is developing examples to support the teams belief that the CAPRs for the Root Cause for the Corrective Action Program may not be fully effective. The plant has completed 123 of 134 corrective actions in this area, yet we have identified CAP problems through this week. Preliminarily, CAPRs 1 and 2 involving the use of SMEs and Use of Performance Indicators appear to be ineffective. 

(No Change) The Engineering, Maintenance, and Programs group is looking at several examples where well established programs have not been followed. There was a circuit breaker replacement (swap) involving 52 circuit breakers covering a wide variety of plant equipment that was not screened under 50.59 as the licensee believed that they were exact, “like for like” replacements. The NRC has determined that lugs used inside of the breakers were a different size, and should have been evaluated accordingly. Other items that may also support this issue (though the mods are very dated): 

The EDG gearbox issue described above 

During a walkdown, an inspector noted that the EDG exhaust didn’t appear to be missile-protected. The exhaust was moved as part of a modification 

Plant Computer modification that impacted the heat balance calculation 

(No Change) The Engineering, Maintenance, and Programs group is looking into several examples of corrective actions that may not have been properly addressed. One involves a 2011 Internal Flooding issue that was raised, and has not yet been fully addressed. 

(No Change) The Engineering, Maintenance, and Programs group is inspecting an issue associated with lack of clearance between grating/ pipe supports and the primary containment liner. The design requires 1/16 “ clearance and in some cases there is no clearance. The licensee wrote and closed 4 CRS without properly evaluating the issue or reviewing extent of condition. We did brief a 10CFR50 AppB Criterion XVI performance deficiency that we are developing 

(Update) We receive a revised Root Cause Evaluation for the 95001 SRV sample on Monday. The teams preliminary review of the document appears to provide an inadequate Root Cause Evaluation and corrective actions that will not prevent recurrence. Essentially, this revised root cause blames Operations Management and an inadequate post trip review. The inspector believes that these may be contributing causes, but the root cause is more aligned to a failure to properly implement the corrective action process. Frank Arner reviewed Doug Dodson’s work and has aligned with Doug’s view that the Root Cause is not adequate. However, there is a possibility, when you evaluate all of the corrective actions taken to date on the issue, that they have taken adequate corrective actions. Doug believes that the Root Cause is an inadequate Operability Determination for the 2013 SRV Failure, and poor corrective actions for what they did put in the CAP. Since ODs and CAP are issues that have had recent actions, we think that they may have taken adequate corrective action. That being said, it is likely that the licensee did not adequately complete the 95001 in that they got the Root Cause wrong. 

(New) Pilgrim has a longstanding (30+Years) issue where the ‘B’ RHR Heat Exchanger bottom flange has been leaking. The have conducted three non-code furminite repairs over the years. The last injection was 2007, and the leakage has reinitiated at 30 drops per minute. Entergy cannot find the paperwork for the first injection, and does not know the type or the amount of material injected. This appears to be a non-code repair of a code system that either needed to be resolved at the next outage, or code relief provided by the NRC. Neither has been done. Additionally, there is current leakage (120 drops/min at 50 psig) outside of the drywell that has not been appropriately evaluated. More to follow on this issue. 

(New) The ECP Manager has not completed the Entergy qualification program. This seems strange for a Column 4 plant where Safety Culture is a fundamental problem area. 

Common Causal Insights:

(No Change) The Safety Culture Group is hearing that people are happy and working to improve the site (Exception- Security). The observation of actual performance however is somewhat disjointed. It appears that many staff across the site may not have the standards to know what “good” actually is. There is a lot of positive energy, but no one seems to know what to do with it, to improve performance, leading to procedural non compliances, poor maintenance, poor engineering practices, and equipment reliability problems. Example- Jeff Josey questioned operability of ‘A’ EDG Wednesday around 10 AM with a well-developed set of questions, and a direct statement questioning operability. By 4pm, we were aware that the Shift Manager was not made aware of this challenge, and no CR was written. The NRC then approached the Shift Manager with the Operability challenge. We are still waiting for the answers to our operability questions (but as mentioned previously, we don’t think there is now an immediate concern). Additionally, while observing an IC surveillance, the worker stated that this test would take him much longer since the NRC was watching. In fact, the channel that we watched took 2.5 hours to complete, and the other 3 Channels took 2 hours total to complete when we were not observing. 

(Update) We became aware today that corrective actions associated with the Recovery Plan are being “kicked back” to the organization by the external contracted review folks after completion by Pilgrim because the closure actions do not match the required actions. In several cases that we have reviewed, station management then changes the recovery action on the CA to match what was actually done, such that the external contracted review group agrees with issue closure. We are capturing examples of this to prove our point. The licensee was in disbelief when we mentioned this issue. One example that we found today is that the Recovery Plan calls for all Supervisors and above to have a “Targeted Performance Improvement Plan” which is tailored to the individual, have milestones, and due dates for specific actions. Apparently the plans are not tailored to the individual and are nearly all the same, and we found that some folks just recently found out that they were on a TPIP, and were surprised. It does not appear that they met the spirit of the recovery action. 

(No Change) Overall, we are beginning to see a picture where the people seem to be willing and happy/excited about change, but actions seem to be marginalized during implementation. Some of this marginalization seems to be due to not understanding what the end state should look like, and frankly some of it seems to be due to a lack of resources across many groups. We will be probing this further, as it is a key to making a recommendation whether or not the plan will be effective/ sustainable.

(New) A licensee oversight contractor informed me that the licensee is actively working a further revision to the Recovery Plan to address the issues that we have found in the last week. They plan to present this to the NRC later this week. I will likely need to discuss this with NRR to figure out the rules on reviewing this. 

Level of Cooperation:

In general, the licensee is being responsive, but very disjointed in their ability to populate meetings and answer questions, staffing problems seem to impact how fast the licensee can respond. For example- We attempted to conduct a safety culture focus group with Security and no one showed up, because the security supervisor “forgot” he needed to support it. The plant seems overwhelmed by just trying to run the station. An RP person wrote a CR last evening that the NRC inspection was significantly impacting getting her work done, and that we should spread out requests over the whole 3 weeks….seemed very frustrated. We have been very clear that we are flexible, and that we are sensitive to impact on plant activities.

The licensee engineering group appears unprepared to address all of the questions being posed by the team. I am couching this by questioning their overall Engineering Acumen. 

My thoughts:

The team is really struggling to figure out what all of this means. The licensee staff seems to say the right things, and they are genuinely energized about improving. We believe that there are some incremental improvements that look bigger than they actually are to the licensee staff. The corrective actions in the recovery plan seem to have been hastily developed and implemented, and some have been circumvented as they were deemed too hard to complete. We are observing current indications of a safety culture problem that a bunch of talking probably won’t fix. We did see a paired supervisory observation that uncovered procedure usage problems that were not directly identified by the workers supervisor. If the 95001 SRV review is truly UNSAT after almost 2 years, my confidence will not be very high, and I reiterate we received a revision dated 4 days ago. The dance associated with EDG operability this week is also disturbing on many levels- Poor Engineering Expertise, no communication with the shift manager, Poor original corrective action, and a Senior Manager stating a reluctance to assure operability due to a negative impact on maintenance rule status. Carey, Frank, and met early on Sunday, and discussed several “themes” that we plan to further develop, namely: Safety Culture, Ineffective CAP, Conduct of Operations/OPS Standards, Engineering Acumen, and Work Management. The challenge will be to determine if Corrective Actions already taken in all of these areas has been effective or not. On the plus side, we have not identified performance deficiencies at the same rate as ANO, and the team believes that procedures are in good shape.

 Very Respectfully

Don Jackson- Team Lead

Leave a Reply